As a Trichy Engineer Trainee, I was well aware of DSS/ DESS and PGMA concepts for Bill of Material. After joining Power Projects division, I was exposed to the package system followed by Hardwar unit for Steam Turbines and Generators. For monitoring the projects we used depend on the Shipping lists provided by Manufacturing units and then check material receipts against Packing list and arrive at pending list. In addition to the main supply, there are additional items, commissioning spares and replacements against Insurance claims. Based on these we would prepare pending list. However a friend in Baroda told that pending list for Hardwar supply cannot be complete without deletion list. It was quite intriguing statement. He explained that Russians/ Germans had standardized number of packages and their contents for TG set. A package was to leave Works only when all items were there. To get the outturn, the unit devised a system of completing a package by deleting the items not ready...